PART 5332 — Contract Financing
Table of Contents
SUBPART 5332.1 — NON-COMMERCIAL ITEM PURCHASE FINANCING
5332.104 Providing Contract Financing
SUBPART 5332.2 - COMMERCIAL ITEM PURCHASE FINANCING
SUBPART 5332.4 — ADVANCE PAYMENTS FOR NON-COMMERCIAL ITEMS
SUBPART 5332.5 — PROGRESS PAYMENTS BASED ON COSTS
5332.501-2 Unusual Progress Payments
SUBPART 5332.6 — CONTRACT DEBTS
5332.607 Installment Payments and Deferment of Collection
SUBPART 5332.7 — CONTRACT FUNDING
5332.703-2 Contracts Conditioned Upon Availability of Funds
INTERIM CHANGES: See CPM 19-C-11 and CPM 20-C-11.
(a)(5) Report known adverse developments affecting a contractor or subcontractor to the contract administration office, other interested Government parties, and the SCO. If there is an adverse development affecting a contractor receiving a bank loan guaranteed by the Air Force, progress payments, or advance payments, the contracting office must report the adverse development, its expected impact upon continued satisfactory performance under the contract, remedial actions taken to date (if any), and any recommendations for further action through the SCO to SAF/AQC.
(c)(2) The contracting officer must submit any unusual financing requests by a contractor to the SCO contracting staff for consultation. If the SCO determines unusual financing is required, the SCO must submit a memorandum outlining the pertinent facts together with a recommendation on the action to be taken through SAF/AQC to SAF/FMF no later than 30 days before the needed effective date of the proposed financing arrangement.
(b) Authorization. The contracting officer must submit all commercial interim payment requests and commercial advance payment requests through the SCO to SAF/AQC for forwarding to SAF/FMF for review and approval. The request must include a staff summary sheet showing the appropriate level of approval with the following attachments: D&F, J&A (if applicable), background paper such as a Milestone Payment Plan that outlines the reason(s) for the request, and the proposed payment schedule. When SAF/FMF has determined the documentation is adequate, they will notify the contracting officer via email. INTERIM CHANGE: See CPM 20-C-11.
(d) Unusual contract financing. See MP5301.601(a)(i).
(e)(2) The contracting officer must submit each advance payment request through the SCO to SAF/AQC for submission to SAF/FMF for review and approval. See MP5332.470 for processing advance payment requests.
(c)(1)(iii) INTERIM CHANGE: See CPM 19-C-11.
(a)(3) The contracting officer must submit contractor requests for unusual progress payments through the SCO to SAF/AQC with a recommendation to approve or disapprove the request. SAF/AQC will forward all requests for unusual progress payments, whether recommended for approval or disapproval, to SAF/FMF with all pertinent data supporting the recommended action for approval and submission to OUSD(A&S)/DPC.
(a) When the estimated contract costs increase such that the estimate of the unusual progress payments increase $20 million or more over the approved unusual progress payment estimate, the contracting officer must notify SAF/FMF through their SCO, with a courtesy copy to SAF/AQC.
(b) Payment information for the demand for payment letter can be found at:
https://www.dfas.mil/contractorsvendors/governmentremittance/returnfunds.html
(e) Contracting officers must retain a copy of all contract debt documentation in the contract file and must keep the contract file open until the debt is collected and/or written-off.
(a) When a request for deferment of a contract debt is received from a contractor, the contracting officer must forward the request for deferment to the SCO. The SCO must submit, on a priority basis, an evaluation of the contractor s request with the necessary reporting information and recommendation through SAF/AQC to SAF/FMF.
(a) Fiscal year contracts. See MP5332.7 on contract funding. See DFARS 204.7103 for guidance on considering severability when forming contracts and determining contract funding.
See AFMC PGI 5332.703.
See SMC PGI 5332.703.
(1)(i)(C)(ii) See MP5301.601(a)(i).
(a) INTERIM CHANGE: See CPM 19-C-11.
(b) INTERIM CHANGE: See CPM 19-C-11.