Subpart 5336.2 - SPECIAL ASPECTS OF CONTRACTING FOR CONSTRUCTION
5336.208 Concurrent Performance of Firm-Fixed-Price and Other Types of Construction Contracts
5336.209 Construction Contracts with Architect-Engineer Firms
5336.213-2 Presolicitation Notices
5336.272 Prequalification of Sources
Subpart 5336.3 - TWO-PHASE DESIGN-BUILD SELECTION PROCEDURES
5336.301 Use of Two-Phase Design-Build Selection Procedures
Subpart 5336.5 - CONTRACT CLAUSES
5336.507 Permits and Responsibilities
5336.570 Additional Provisions and Clauses
Subpart 5336.6 - ARCHITECT-ENGINEER SERVICES
Subpart 5336.2 - SPECIAL ASPECTS OF CONTRACTING FOR CONSTRUCTION
5336.208 Concurrent Performance of Firm-Fixed-Price and Other Types of Construction Contracts
5336.209 Construction Contracts with Architect-Engineer Firms
5336.213-2 Presolicitation Notices
5336.272 Prequalification of Sources
Subpart 5336.3 - TWO-PHASE DESIGN-BUILD SELECTION PROCEDURES
5336.301 Use of Two-Phase Design-Build Selection Procedures
(b)(3)(vi) See MP5301.601 (a)(i) Head of the Contracting Activity (HCA) Matrix.
5336.303-1 Phase One
(a)(4)(i)(B)See MP5301.601 (a)(i) Head of the Contracting Activity (HCA) Matrix.
Subpart 5336.5 - CONTRACT CLAUSES
5336.507 Permits and Responsibilities
When the clause at FAR 52.236-7, Permits and Responsibilities, is used in solicitations and contracts OCONUS, the clause must be modified to reflect “host government and political subdivisions” in lieu of “Federal, State, and Municipal.”