VAAR PART 815--CONTRACTING BY NEGOTIATION



PART 815--CONTRACTING BY NEGOTIATION

Authority: 40 U.S.C. 121(c) and 48 CFR 1.301–1.304.

Subpart 815.3--Source Selection

815.303 Responsibilities.

The authority of the Secretary to appoint an individual other than the contracting officer to serve as the source selection authority for a particular acquisition or group of acquisitions is delegated to the SPE and is further delegated to the DSPE. If an HCA wishes to designate an individual other than the delegated contracting officer as the source selection authority for a particular acquisition or group of acquisitions, the HCA shall prepare a request and justification and shall submit the request through channels to the DSPE for approval.

Subpart 815.4--Contract Pricing

815.404 Proposal analysis.

815.404-1 Proposal analysis techniques.

(a) Contracting officers are responsible for the technical and administrative sufficiency of the contracts they enter into. Contracting officers must ensure that contracts undergo all applicable legal and technical reviews. (See 801.602-70.)

(b) Contracting officers determine the level of technical analyses necessary for initial and revised pricing of all negotiated prime contracts, including subcontract pricing under them, and contract modifications. Contracting officers must request technical analyses of the proposals from the appropriate technical personnel. The technical analyses must address, as a minimum, the items set forth in FAR 15.404-1(e)(2).

(c) The contracting officer must document the results of such analyses in the contract file and make the results available to the auditor performing the pre-award audit.

815.404-2 Information to support proposal analysis.

In evaluating start-up and other non-recurring costs, the contracting officer must determine the extent to which these costs are included in the proposed price and the intent to absorb or recover the costs in any future noncompetitive procurement or other pricing action. The contracting officer must ensure, with the assistance of the Assistant Inspector General for Policy, Planning, and Resources, as required or considered necessary, that VA will not pay the costs twice. For example, the cost of equipment that the Government pays for through a setup or connection agreement must not be included in depreciation cost of a subsequently negotiated agreement.

Subpart 815.6--Unsolicited Proposals

815.604 Department points of contact.

A VA employee who receives an unsolicited proposal or inquiries from a potential offeror of an unsolicited proposal must refer the proposal or inquiries to the following:

(a) Facility level unsolicited proposals must be referred to the HCA for the field facility.

(b) Proposals to the VA National Acquisition Center must be referred to the Executive Director and Chief Operating Officer, VA National Acquisition Center.

(c) Proposals to VA Central Office must be referred to the Director, Acquisition Operations Service (049A3).

815.606 Department procedures.

(a) The VA contact point will do the following:

(b) The contact point will maintain a record of advance guidance provided and the disposition/recommendation regarding the potential offer.

(c) The contact point will review the unsolicited proposal and ensure that it is complete as prescribed in FAR 15.605. If required information is not submitted, the contact point will:

815.606-1 Receipt and initial review.

(a) When the VA contact point determines a proposal warrants a comprehensive evaluation (i.e., the proposal complies with the requirements in FAR 15.606-1(a) and is related to VA’s mission), the contact point must contact the offeror to ensure that all data that should be restricted in accordance with FAR 15.609 has been identified.

(b) The contact point must maintain a log of all unsolicited proposals to be evaluated. The log must indicate the following:

(c) The contact point must advise each office assigned responsibility for reviewing an unsolicited proposal of the need to evaluate the proposal against the criteria set forth in FAR 15.607(a)(1) through (4). If the reviewers determine that the proposal fails to meet any of the criteria, the contact point must be advised. The contact point must return the proposal to the offeror, citing the reasons therefore.

(d) The contact point must obtain approval of the DSPE (049A5) before the contact point, if warranted as a contracting officer, or an appropriate contracting officer begins negotiation on proposals. The contact point must provide the DSPE (049A5) all necessary documentation supporting the noncompetitive negotiation, including any justification and approval required by FAR Subpart 6.3 and the results of any synopsis required by FAR Subpart 5.2. The DSPE (049A5) will consult the appropriate VA Central Office program official(s) and return the final decision to the contact point.