SUBJECT: Automatic Data Processing Equipment Leasing Costs
We have amended Part 239 of the Defense Federal Acquisition
Regulation Supplement (DFARS) to remove references to the deleted
Federal Acquisition Regulation (FAR) cost principle at 31.205-2,
Automatic Data Processing Equipment Leasing Costs, and to remove
corresponding contractor documentation and Government oversight
requirements at DFARS 239.73, Acquisition of Automatic Data
Processing Equipment by DoD Contractors.
This interim DFARS rule is effective immediately and will be
included in a future Defense Acquisition Circular.
/s/
Eleanor R. Spector
Director, Defense Procurement
Attachment
cc: DSMC, Ft. Belvoir
DFARS CASE 96-D011
SUBPART 239.73--ACQUISITION OF AUTOMATIC DATA PROCESSING
EQUIPMENT BY DOD CONTRACTORS
239.7300 Scope of subpart.
This subpart prescribes approval requirements for automatic data processing
equipment (ADPE) purchased by contractors for use in
performing DoD contracts.
239.7301 Applicability.
- (a) This subpart applies when [t]he contractor [purchases] ADPE and title will pass to the Government(.)
* * * * *
239.7302 Approvals and screening.
* * * * *
- (b) If the contractor proposes acquiring ADPE subject to 239.7301, and the unit
acquisition cost is $50,000 or more--
- (1) The contracting officer shall require the contractor to submit, through the administrative contracting officer, the documentation in 239.730[3].
* * * * *
239.730[3] Contractor documentation.
Contracting officers may tailor the documentation requirements in paragraphs (a)
through ([d]) of this section.
- (a) List of existing ADPE and an analysis of its use.
- (1) List of each component identified by manufacturer, type, model
number, location, date of installation, and how acquired (lease, purchase,
Government-furnished). Identify those acquired specifically to perform a
Government contract.
- (2) Reliability and usage data on each component for the past 12 months.
- (3) Identification of users supported by each component, including how much time each user requires the component and the related contract or task involved.
- (1) List of each component identified by manufacturer, type, model
number, location, date of installation, and how acquired (lease, purchase,
Government-furnished). Identify those acquired specifically to perform a
Government contract.
- (1) Estimates of the new equipment's useful life.
- (2) List of tasks the new equipment is needed for and why, including
estimated monthly usage for each major task or project.
- (3) Anticipated software and telecommunications requirements.
- (1) If the acquisition is competitive--
- (i) List sources solicited and proposals received;
- (ii) Show how the evaluation was performed;
- (iii) Provide an explanation if the selected offer is not the lowest evaluated offer.
- (i) List sources solicited and proposals received;
Table 39.1 is deleted.
* * * * *