AFMCFAR SUPPLEMENT (2007 Edition)

The following changes are a result of approval of FAR Case 08-01:

AFMCFARS 5301 – FAR Systems

5301.108 FAR Conventions (90)

• Add—Insert new paragraph (c) (ix) for defective pricing actions to prescribe use of the DCAA Recommended Price Adjustment (RPA) as the dollar value of defective pricing actions for clearance and other thresholds.

• Renumber former paragraph (c)(ix) as (x).

AFMCFARS 5315 – Contracting by Negotiation

5315.407-1 – Defective Cost or Pricing Data

Revise to require at least one level above the contracting officer when either the negotiation objective or the negotiated amount deviates from the DCAA RPA.

The following changes were inadvertent omissions from publication of the 2007 Edition and/or administrative changes:

AFMCFARS 5301 – FAR Systems

5301.9001 Policy, thresholds and approvals

Updated organization table to reflect administrative changes:

      o Deleted AAC/329 ARSG

      o Added ASC/516 AESW/653

      o Deleted ASC/PKN

      o Added ASC/PKF

      o Added ASC/77 AESW/664 AESS

AFMCFARS 5304 – Administrative Matters

5304.100-90 Mandatory Use Policy for Contract Writing Systems

Added -- Incorporated Policy Memo, dtd 7 Dec 07; subject: Mandatory Use of Contract Writing Systems, Updated 30 Oct 07, into the Supplement. The Policy Memo is rescinded upon issuance of this AFMCAC 07-01.

5304.201-90 Use of Paper and Electronic Document Distribution

Revised to add / clarify Mandatory Use Policy for Electronic Contract Distribution through Contract Writing Systems. Same Policy Memo as above.

IG5304.201.90 Use of Paper and Electronic Document Distribution

Mandatory electronic distribution requirement moved to the Supplement

AFMCFARS 5307 – Acquisition Planning

5307.104-92(d)(5)(90) AFMC Alternate Procedures and Thresholds for “Non-operational” Other Contracting Acquisitions

Revised to correct an inadvertent omission from 2007 Edition – S&T actions

AFMCFARS 5313 – Simplified Acquisition Procedures

5313.305-3(d)(90) Simplified Acquisition Methods

Correction -- The threshold is $3000 per FAR 13.003 -- Policy.

AFMCFARS (2007 Edition)

AFMCFARS 5343 – Contract Modifications

5343.102-90 Contract scope considerations

Added to correct inadvertent omission from 2007 Edition – ESC/CC Mandatory Scope Policy

IG5343.103 Types of Contract Modifications

Corrected last item in Table