Subpart 436.5 - Contract Clauses

436.500 Scope of subpart.

This subpart prescribes clauses for insertion in USDA solicitations and contracts for construction and for dismantling, demolition, or removal of improvements or structures. The contracting officer shall use the clauses as prescribed, in contracts that exceed the simplified acquisition threshold. The contracting officer may use the clauses if the contract amount is expected to be within the simplified acquisition threshold.

436.571 Prohibition against the use of lead-based paint.

The contracting officer shall insert the clause at 452.236-71, Prohibition Against the Use of Lead-Based Paint, in solicitations and contracts, if the work involves construction or rehabilitation (including dismantling, demolition, or removal) of residential structures. This clause may be used in contracts for other than residential structures.

436.572 Use of premises.

The contracting officer shall insert the clause at 452.236-72, Use of Premises, if the contractor will be permitted to use land or premises administered by USDA.

436.573 Archeological or historic sites.

The contracting officer shall insert the clause at 452.236-73, Archeological or Historic Sites, if the contractor will be working in an area where such sites may be found. Use of the clause is optional in service contracts for on-the-ground work, e.g., reforestation, silvicultural, land stabilization, or other agricultural-related projects.

436.574 Control of erosion, sedimentation, and pollution.

The contracting officer shall insert the clause at 452.236-74, Control of Erosion, Sedimentation and Pollution, if there is a need for applying environmental controls in the performance of work. Use of the clause is optional in service contracts for on-the-ground e.g., reforestation, silvicultural, land stabilization, or other agricultural-related projects.

436.575 Maximum workweek-construction schedule.

The contracting officer shall insert the clause at 452.236-75, Maximum Workweek-Construction Schedule, if the clause at FAR 52.236-15 is used and the contractor's work schedule is restricted by access to the facility or must be coordinated with the schedule of contract administration personnel.

436.576 Samples and certificates.

The contracting officer shall insert the clause at 452.236-76, Samples and Certificates, in all contracts.

436.577 Emergency response.

The contracting officer may insert the clause at 452.236-77, Emergency Response, in construction contracts awarded for the Forest Service.

436.578 Contract clause.

Insert the clause at 452.236-78, Fire Suppression and Liability in solicitations and contracts for Integrated Resource Service Contracts (IRSC) awarded for the Forest Service.

436.579 Opted timber sale road requirements.

The contracting officer shall insert the clause at 452.236-79, Opted Timber Sale Road Requirements, in road construction contracts resulting from a timber sale turnback.