Subpart 5304.1 - CONTRACT EXECUTION

Subpart 5304.1 - CONTRACT EXECUTION

5304.101 Contracting Officer’s Signature

Contracting officers are required to sign all contract actions (either via wet signature, signature as produced by CON-IT, or digital signature produced with a DoD Public Key Infrastructure certificate using a Common Access Card), ensure contractor signatures are obtained, and maintain signed contractual documents within the official contract file.

5304.102 Early Effective Date

1. Approval authority for the use of an early effective date is the chief of the contracting office. After reaching agreement on terms, conditions, price, and if funds are available, the contracting officer may advise a prospective contractor in writing of the Government’s intent to use an effective date before the contract mailing (award/signed) date.

2. Notice to the contractor should state that any costs recognized in a resulting contract should be limited to those allowable, allocable and reasonable; costs that would normally be recognized if incurred after contract award. The Notice to the contractor should state, that if there is no contract, all incurred costs should be at the contractor’s own risk.

3. Approval Authority should provide contractual coverage with a letter contract, or other appropriate undefinitized contractual action, if the Government intends to direct a prospective contractor, to accept benefits of efforts, or make payments before definitive contract mailing date.