Skip to main content
GSAM

GSAM

Change Number: Change 178 GSAR Case 2020-G511
Effective Date: 03/25/2024

Subpart 536.5 - Contract Clauses

Subpart 536.5 - Contract Clauses

536.506 Superintendence by the contractor.

Insert the clause at 552.236-6, Superintendence by the Contractor, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated.

536.511 Use and possession prior to completion.

Insert the clause at 552.236-11, Use and Possession Prior to Completion, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated.

536.515 Schedules for construction contracts.

Insert the clause at 552.236-15, Schedules for Construction Contracts, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause-

(a)With its Alternate I when the contract amount is expected to exceed the simplified acquisition threshold and a design-bid-build project delivery method will be followed; or

(b)With its Alternate II when the contract amount is expected to exceed the simplified acquisition threshold and a design-build project delivery method will be followed.

(c)With its Alternate III when the contract amount is expected to exceed the simplified acquisition threshold and a construction-manager-as-constructor project delivery method will be followed.

536.521 Specifications and drawings for construction.

Insert the clause at 552.236-21, Specifications and Drawings for Construction, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause with its Alternate I when a design-build project delivery method will be followed—

(a)  With its Alternate I when a design-build project delivery method will be followed.

(b)  With its Alternate II when a construction-manager-as-constructor project delivery method will be followed.

536.570 Authorities and limitations.

Insert the clause at 552.236-70, Authorities and Limitations, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated.

536.571 Contractor responsibilities.

Insert the clause at 552.236-71, Contractor Responsibilities, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause:

(a)  With its Alternate I when a design-build project delivery method will be followed.

(b)  With its Alternate II when a construction-manager-as-constructor project delivery method will be followed.

536.572 Submittals.

Insert the clause at 552.236-72, Submittals, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause with its Alternate I when a design-build project delivery method will be followed.

536.573 Subcontracts.

Insert the clause at 552.236-73, Subcontracts, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated.