4.804-4 Physically completed contracts.

My Favorites


4.804-4 Physically completed contracts.

4.804-4 Physically completed contracts.

      (a)Except as provided in paragraph (b) of this section, a contract is considered to be physically completed when-

           (1)

(i)The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;

                (ii)The contractor has performed all services and the Government has accepted these services; and

                (iii)All option provisions, if any, have expired; or

           (2)The Government has given the contractor a notice of complete contract termination.

      (b)Rental, use, and storage agreements are considered to be physically completed when-

           (1)The Government has given the contractor a notice of complete contract termination; or

           (2)The contract period has expired.